§ 15-10. Same—Certificates of approval.  


Latest version.
  • The inspector shall issue a certificate of approval at the completion of the work for which a permit for consumer piping required by section 15-29 has been issued, if, after the inspection required by section 15-8 it is found that such work complies with the provisions of this chapter. A duplicate of each certificate issued covering consumer's gas piping shall be delivered to the gas company and used as its authority to render gas service.

(Ord. No. 1029, § 9, 9-11-72)